  • Time table

    Planning

    The contract period for EUPHIX is from 1 July 2004 to 30 June 2008.


    15 November 2007
    EUPHIX workplan
    Time table and milestones


    Description time table

    The activities are divided in Work Packages. One Full Project Meeting (FPM) will be held roughly every six months. We plan to offer an improved version of the web application, called ‘Integrated Pilot’, for each FPM.

    In the first half of the project period we will focus on the basic web technology aspects and database functionalities, while the production of the content will be in focus in the second half. More attention will be given to the links with other EU projects and activities in the second half as well.

    Milestones (IP1.1-1.4, 2.0) are marked in the time table.

    Time table

    Time

    WPc1

    WPc2

    WPc3

    WPc4

    Year-months

    Management, sustainability

    Content

    Application

    Networks

    2005/ 4-7

    Elaborate project aims; 1st FPM June 9-10

    First designs for content structure

    First designs for application; writing functional design

    Plan for establishing of the expert network

    2005/ 8-10

    Organise work in RIVM EUPHIX team; employ a broader expertise in RIVM/VTV

    Elaborate the basics of EUphact/EUphocus structure

    Develop Work-in-Progress (WiP) site

    PR activities: leaflet, EUPHA presentation

    2005/ 11 to 2006/ 1

    Prepare integrated pilot 1.1; organise next FPM

    Prepare pilot application (2 EUphoci, 6 EUphacts)

    Prepare pilot application; develop database and map production

    2006/ 2-3

    2nd FPM 2-3 February :IP 1.1; discuss first pilot; expand contacts with DG SANCO

    Consolidate pilot with partners, reviewers; select 2 new EUphoci, 5-7 new EUphacts

    Consolidate pilot with partners, reviewers

    Start building networks and partner co-operation for new EUphacts, EUphoci

    2006/ 4-8

    Prepare next meeting; work with partners

    Start work on new EUphacts/EUphoci; devise publishing procedures

    Implement the adapted style sheet. Develop further application tools: database, maps, graphs

    Work with partners; establish target group panel

    2006/ 9-12

    3rd FPM 19-20 October, Luxembourg: IP1.2; discuss improvements oand additions to the first pilot, further plans; expand PR activities. Consider conditions for sustainable maintenance

    Implement new EUphoci and associated EUphacts; implement production protocols on editing and reviewing. Select and start on 2 new EUphoci, 6-8 new EUphacts; start work on policy overviews

    Implement standards in database; production of tables, graphs, maps. Consider maintenance after end of project

    Consult target group panel. Establish inventory of network partners

    2007/ 1-4

    4th FPM April: IP 1.3; discuss system extensions; further plans;

    Implement new EUphoci and EUphacts; select extra EUphacts to cover (part of) the ECHI shortlist

    Adaptations for maintenance outside RIVM?

    Continue involvement of partners, networks

    2007/ 5-8

    IP 1.4

    Have more ECHI shortlist EUphacts covered; draft policy overviews

    Prepare for handing over, depending on success application

    2nd consultation target group panel

    2007/ 9-12

    5th FPM November:IP 2.0; agreement on project finalisation

    Last update of EUphacts and EUphoci

    Last update of technical improvements

    2008/ 1-6

    Prepare final report; final web site release; transfer to SANCO

    Consolidation of content

    Consolidation

    Consolidation and establishment of the EUPHIX network

    Milestones

    Deliverables are indicated in the columns corresponding to the Work Packages. In the column WPc 1 (management), five ‘integrated pilots’ are mentioned. These integrated pilots are accessible only for the EUPHIX team at the RIVM and for the project partners.

    These can be roughly described as:

    IP 1.1: The web site environment is experimental, the content is implemented as drafts, serving as examples for the first discussion of the structure and content.

    IP 1.2: The web site environment is substantially upgraded, the content elements are reviewed, EUphacts extended by the first two EUphoci on smoking and obesity. Some exchange of expertise with project partners has been implemented.

    IP 1.3: Limited upgrade of the web site environment; substantial extension of EUphoci and EUphacts, increasingly using the expertise of the project partners, the expert networks and the target group panel.

    IP 1.4: Consolidation of web site environment; further extension of indicator-related EUphacts. Focus on sustainability of the system.

    IP 2.0: The final product of the EUPHIX project. A functioning prototype including information on a variety of ECHI shortlist indicators, and a set of policy-relevant health EUphoci; a network of experts and the procedures for further maintenance are set up